Recent Posts
ADM-DiP GREEN Gantt Chart
Here is the Gantt chart for our group!
DIP project - Blue Group progress update
We are currently figuring ways to render different kinds of light to have it closely present what we envision they will look like in the location of MBS. We are also exploring the placement of each sculpture in relation to one another, so they are not packed too tightly together, but also give users a visual connection.
ADM-DIP GREEN – Development Process Update
Our aim for this week is to finish up the physical form of the flowers earlier so we can pass parts of the flowers to IEM people to do up wiring. We will also be start filming part of the video this weekend!
Considering the timeline, all 5 of us have meet up a few times over the week to make Read more →
ADM-DIP GREEN - Development Process [Discussion on 25 OCT 2017]
The progress that we aim for this week:
Collection of plastic cups:
We have place notice and boxes at strategic area to collect from our fellow adm peeps. The collection point are located at B1, Level 1 and Level 2 beside the dustbin where mainly student would gather around. We also posted on ADM Facebook page to giving them a heads up Read more →
[Documentation] DiP-ADM Green - Areas of Improvement
Pushing aside the improvements we have made — as mentioned by Suhwee in an earlier post, one of the biggest area for us to improve on is how we can incorporate sound into our installation.
Sound has always been the component that is most underdeveloped for our installation. As of now, our idea is limited to simply using chimes to illustrate Read more →
[Documentation] ADM-DIP Green Group - Light Patterns Development
ADM-DIP Green
As our installation focuses primarily on light pattern to give the visual impact to viewers, we have tried a few light patterns over the past 2 weeks.
*All the GIFs here are the TOP view of one cluster of our installation. As all the stalks are laid in a circular cluster.
1. Circular-Outward Pattern Read more →
ADM-DIP GREEN - Development Process [Discussion on 16 OCT 2017]
After the presentation, we have taken the feedback in to consideration and made some possible improvement.
Ideas Improvements:
Animation (Light Pattern) – Cater to high number of people– Changes according to the distance of the people to the sensor, no longer about how many people within the installation
– Can also play with colour of light such as cool colour to prevent misleading ideas Read more →
ADM-Red Team - Progress Update
After the iLight site visit, we have decided that we would like to put our installation under the bridge near the Esplanade area.
The consideration why we choose this location:
Sheltered, will not interfere with the circuitry that we are going to install. This is a less crowded place, will be able to show interaction more noticeable.As for the project itself, we Read more →